Process about fountain projects .
1. Goverment or Investors make an investment decision for fountain project.
2. By the professional company to complete the design and budget pricing. (Usually takes 15 days)
3. Goverment or Investors make the decision for the final plan and budget. (Usually takes 10 days)
4. Choose the professional company to talk about the cooperation details and sign the contract. (Usually more than 15 days)
5. Goverment or Investors finish the pool's civil work, like the water supply,power,and control room. (Usually more than 15 days)
6.For the project,fountain company should Pre-purchase Pumps,cable and so on, and manufacturing fountain pipes and nozzles. (Usually small project takes 30 days,big project takes 60 days or more)
7.The fountain equipment package and shipment to the Destinations. (Usually takes 30 days or more)
8.On-site installation, commissioning, formal fountain show. (Usually takes 20~30 days or more)
The No.5&6 can do at the same time.So the total time takes about 4 months, if special circumstances can be shortened one month. But your project is big project,so i think maybe more than 5month.
Let me know your project:
1. Fountain Type. (Musical/Non-music)
2. Fountain Site & Size (picture or CAD drawing with size and water quality )
3. The budget for fountain.
4. Special Requirements
Ray Shao
Project manger
Hangzhou West-Lake Fountain Installation Serials Co., Ltd.
Cell:0086 138 5712 7700
Web:www.jl-penquan.com